Multiple Choice
Hamid, a project manager, has a workload of 24,000 hours that needs to be completed in 75 workdays. He has a team of 40 people who work for five 8-hour days per week. In those 75 days, 20 people have each requested three days off at different times. In this scenario, the workload is _____ of capacity
A) 80 percent
B) 102 percent
C) 95 percent
D) 75 percent
E) 150 percent
Correct Answer:

Verified