Multiple Choice
Walter, a project manager in a design agency, is using a project management software to manage his project. The agency he works for is currently prioritizing other projects and needs to conserve scarce resources. In the context of priority rules for allocating resources, which of the following rules should Walter use?
A) Longest task duration first
B) As soon as possible
C) As late as possible
D) Most critical followers
E) Least successors
Correct Answer: