The Following Describes Which Priority Rule: Activities Are Scheduled to Start

Question 37

Multiple Choice

The following describes which priority rule: Activities are scheduled to start on their earliest start times (ES) , and resources are made available with that in mind.


A) As soon as possible
B) As late as possible
C) Shortest task duration first
D) Minimum slack first
E) Most critical followers