    When Two or More Paths Through a Network Join, Even
Solved

When Two or More Paths Through a Network Join, Even

Question 52

Question 52

True/False

When two or more paths through a network join, even at the end of the network, paths that have little slack and/or high variance may become critical simply by chance.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q47: Which of the following terms is most

Q48: It is easiest to see lead and

Q49: A series of connected activities (or intermediate

Q50: The tasks of project planning, project budgeting,

Q51: Organ Bennett Inc., a public relations firm,

Q53: Events in a project consume no resources

Q54: A disadvantage of using beta distribution to

Q55: AON and AOA networks can both be

Q56: A project schedule is a project action

Q57: The difference between EST and LFT is

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines