Multiple Choice
Paul, the marketing manager of a food company, created a diagram of nodes to represent the marketing process for a new product of the company. Each node represented an activity in the marketing process, and an arc joined each node. He used this diagram to demonstrate the objectives of the marketing process. In the context of the language of the Program Evaluation and Review Technique (PERT) and the Critical Path Method (CPM) , the diagram used by Paul is known as a _____.
A) network
B) flowchart
C) Gantt chart
D) Smith chart
E) control chart
Correct Answer:

Verified
Correct Answer:
Verified
Q13: A start-to-finish linkage is the most common
Q14: A situation where two or more activities
Q15: The difference between the LST and EST
Q16: Henry Gantt developed the Gantt chart.
Q17: Rico Gen, a sports apparel manufacturing company,
Q19: Identifiable and noteworthy events marking significant progress
Q20: Agile velocity is not impacted by the
Q21: Gantt charts are not adequate replacements for
Q22: When it was originally developed, PERT used
Q23: Critical path tasks always have zero free