Multiple Choice
Which type of precedence diagramming convention is the following: Activity 7 must be complete at least 1 day before Activity 8 is completed.
A) Finish to start
B) Start to start
C) Finish to finish
D) Start to finish
E) Delay to start
Correct Answer:

Verified
Correct Answer:
Verified