Multiple Choice
Rachel, a project manager, has undertaken a project to build a wall around a compound. She estimates that the cost of materials will be $520 and labor costs will be $10 for 20 hours. If the overheads for this project are 50 percent of the labor and material costs, the total cost will be:
A) $1080.
B) $1,560.
C) $880.
D) $780.
E) $960.
Correct Answer: