Devon, a Project Manager, Is Working on a Software Development

Question 56

Multiple Choice

Devon, a project manager, is working on a software development project. He needs more coders to complete the project on time. As a result, he hires people and they are given on-the-job training by their coworkers. However, this significantly reduces the output of the team and leads to a delay in the project. The given scenario exemplifies:


A) integration management.
B) systems engineering.
C) the mythical man-month effect.
D) the boomerang effect.
E) the sleeper effect.

Correct Answer: