Multiple Choice
Robert, a project manager, created a work breakdown structure (WBS) for his new project. He then used the data from the WBS to create a table that assigned responsibilities to each team member and helped organize the project team. In this scenario, Robert created a(n) _____.
A) Failure Mode and Effect Analysis (FMEA) chart
B) RACI Matrix
C) Langley histogram
D) Gozinto chart
E) contingency plan