Laura worked with a cross-functional team on a project. After the completion of the project, she held a meeting with the team members after which they returned to their respective departments. Which of the following phases of team development does this scenario exemplify?
A) Storming
B) Norming
C) Performing
D) Adjourning
E) Forming
Correct Answer:

Verified
Correct Answer:
Verified