If the Following Jobs Are Sequenced According to the SPT

Question 93

Multiple Choice

If the following jobs are sequenced according to the SPT rule, then the mean tardiness (in days) for all the jobs is (assume zero for today's date) If the following jobs are sequenced according to the SPT rule, then the mean tardiness (in days)  for all the jobs is (assume zero for today's date)    A)  16 days. B)  13 days. C)  5.2 days. D)  3.2 days.


A) 16 days.
B) 13 days.
C) 5.2 days.
D) 3.2 days.