If the following jobs are sequenced according to the SPT rule, then the maximum job tardiness (in days) is (assume zero for today's date)
A) 26 days.
B) 16 days.
C) 10 days.
D) 5.2 days.
Correct Answer:

Verified
Correct Answer:
Verified