Multiple Choice
If the following jobs are sequenced according to the LPT rule, then the maximum job tardiness (in days) is (assume zero for today's date)
A) 7 days.
B) 10 days.
C) 20 days.
D) 25 days.
Correct Answer:

Verified
Correct Answer:
Verified