Multiple Choice
Four products (1, 2, 3, and 4) must be processed on one of the four machines (A, B, C, and D) . The times required in minutes for each product on each machine are shown below: The minimum time required to complete all the products is
A) 29 minutes.
B) 27 minutes.
C) 33 minutes.
D) 36 minutes.
Correct Answer:

Verified
Correct Answer:
Verified
Q30: If the following jobs are sequenced according
Q31: What is the difference between infinite and
Q32: The following set of jobs must be
Q34: Increasing the capacity of a work centre
Q34: The sequencing rule that minimizes average tardiness
Q36: If the following jobs are sequenced according
Q40: Scheduling using the theory of constraints (TOC)
Q66: If a job is ahead of schedule,then
Q70: The time required to complete a group
Q73: Who developed the theory of constraints (TOC)and