Multiple Choice
Which of the following best describes a scheduling technique that sequences jobs as part of the loading decision and where resources are never loaded beyond capacity?
A) finite scheduling
B) infinite scheduling
C) advanced planning and scheduling
D) load levelling
Correct Answer:

Verified
Correct Answer:
Verified