A firm has the following gross requirements for Item F. If ordering costs are $60 per order and carrying costs are $0.50 per period. If L4L ordering is used the planned order releases would be
A) 40 in period 1 and 0 in period 3.
B) 80 in period 2 and 60 in period 3.
C) 60 in period 2 and 80 in period 3.
D) 0 in period 1 and 40 in period 3.