Multiple Choice
A firm has the following gross requirements for Item F. If ordering costs are $60 per order and carrying costs are $0.50 per period. If EOQ lot sizing is used to set the minimum order quantity, then the projected on hand quantity at the end of period 3 would be
A) 40.
B) 0.
C) 100.
D) 20.
Correct Answer:

Verified
Correct Answer: