A company is developing a linear programming model for its aggregate production plan. If Wt = workforce size for period t, Ht = number of workers hired for period t, and Ft = number of workers fired for period t, then the company's workforce constraint for period 4 is
A) W4 = W3 - H4 + F4.
B) W4 = W3 + H4 - F4.
C) W4 = W3 + H3 - F3.
D) W4 = W3 + H4.