Multiple Choice
A tracking signal is computed by
A) multiplying the cumulative error by MAD.
B) multiplying the absolute error by MAD.
C) dividing MAD by the cumulative absolute error.
D) dividing the cumulative error by MAD.
Correct Answer:

Verified
Correct Answer:
Verified