Slack refers to which of the following?
A) the latest time an activity can be finished without delaying the project
B) the amount of time an activity can be delayed without delaying the project
C) the earliest time an activity can be started without delaying the project
D) the latest time an activity can be started without delaying the project
Correct Answer:

Verified
Correct Answer:
Verified