The Following Table of Probabilistic Time Estimates (In Weeks) and Activity

Question 50

Multiple Choice

The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Table 9.3
The following table of probabilistic time estimates (in weeks)  and activity predecessors are provided for a project. Table 9.3   -Using Table 9.3, how much slack is associated with activity C? A)  0 weeks. B)  4.50 weeks. C)  12.67 weeks. D)  31.00 weeks.
-Using Table 9.3, how much slack is associated with activity C?


A) 0 weeks.
B) 4.50 weeks.
C) 12.67 weeks.
D) 31.00 weeks.