The amount of time by which an activity is reduced is known as the


A) normal time
B) crash time
C) optimistic time
D) pessimistic time

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q1: A project consists of the following activities:<br>

Q12: A Gantt chart provides a visual display

Q24: A project's duration can be reduced by

Q29: Project scope involves a set of procedures

Q34: Project planning involves a set of procedures

Q41: Enterprise project management refers to the management

Q45: In general,crashing costs decrease as a project's

Q81: Which of the following is not a

Q88: Explain the basics of project scheduling and

Q90: The project management process encompasses<br>A) planning.<br>B) scheduling.<br>C)

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines