As part of its quality-improvement program, a company is conducting a time study for a particular job. The time study encompassed 10 job cycles, and the results include the following cumulative times and performance rating factors for each element: The standard time for this job, using an allowance factor of 16%, is
A) 1.809 minutes.
B) 2.098 minutes.
C) 1.530 minutes.
D) 2.233 minutes.