The Direct Labour Time Required to Produce the First Sailboat

Question 125

Multiple Choice

The direct labour time required to produce the first sailboat of a particular model was 3000 hours. If the company believes that an 80% learning curve applies to the production of this model sailboat then the direct labour time required to produce the 2nd boat is estimated to be


A) 600 hours.
B) 2,400 hours.
C) 3,600 hours.
D) 4,000 hours.