Multiple Choice
The shortest possible time in which an entire project can be completed if all project tasks go according to plan is the:
A) critical path.
B) job duration.
C) project calendar.
D) PERT summary.
E) project objective.
Correct Answer:

Verified
Correct Answer:
Verified