Multiple Choice
A job has an 80 percent learning curve. If the first unit took 40 hours to complete, the fourth unit should take roughly how many hours?
A) 20
B) 25
C) 31
D) 35
E) 40
Correct Answer:

Verified
Correct Answer:
Verified