A company is designing a product layout for a new product. It plans to use this production line 8 hours a day in order to meet projected demand of 480 units per day. The tasks necessary to produce this product are:
Without regard to demand, what is the minimum possible cycle time (in seconds) for this situation?
A) 162
B) 72
C) 54
D) 30
E) 6
Correct Answer: