A company is designing a product layout for a new product. It plans to use this production line 8 hours a day in order to meet projected demand of 480 units per day. The tasks necessary to produce this product are:
A company is designing a product layout for a new product. It plans to use this production line 8 hours a day in order to meet projected demand of 480 units per day. The tasks necessary to produce this product are:   If the company wants the output rate to be equal to demand, what is the theoretical minimum number of workstations needed? A) 3 B) 4 C) 5 D) 6 E) 7
If the company wants the output rate to be equal to demand, what is the theoretical minimum number of workstations needed?