A company is designing a product layout for a new product. It plans to use this production line 8 hours a day in order to meet projected demand of 480 units per day. The tasks necessary to produce this product are:
A company is designing a product layout for a new product. It plans to use this production line 8 hours a day in order to meet projected demand of 480 units per day. The tasks necessary to produce this product are:   If the company wants the output rate to be equal to demand, what would be the efficiency of this line with the theoretical minimum number of workstations? A) 100 percent B) 92.5 percent C) 75 percent D) 87.5 percent E) 90 percent
If the company wants the output rate to be equal to demand, what would be the efficiency of this line with the theoretical minimum number of workstations?


A) 100 percent
B) 92.5 percent
C) 75 percent
D) 87.5 percent
E) 90 percent