A Company Is Designing a Product Layout for a New

Question 72

Multiple Choice

A company is designing a product layout for a new product. It plans to use this production line 8 hours a day in order to meet projected demand of 480 units per day. The tasks necessary to produce this product are:
A company is designing a product layout for a new product. It plans to use this production line 8 hours a day in order to meet projected demand of 480 units per day. The tasks necessary to produce this product are:   If the company wants the output rate to be equal to demand, what is the last task performed at the second workstation if tasks are assigned in order of the most following tasks? A) u B) v C) w D) x E) y
If the company wants the output rate to be equal to demand, what is the last task performed at the second workstation if tasks are assigned in order of the most following tasks?


A) u
B) v
C) w
D) x
E) y