Multiple Choice
QRS Corp. is designing a product layout for a new product. They plan to use this production line 10 hours a day in order to meet forecasted demand of 900 units per day. The following table describes the tasks necessary to produce this product:
For output to equal forecasted demand, what is the theoretical minimum number of workstations needed?
A) 1
B) 3
C) 3.75
D) 4
E) 5
Correct Answer:

Verified
Correct Answer:
Verified