A company has an assembly line with 34 tasks. The longest task is 4.7 minutes and the total time for all tasks is 92 minutes. The line will operate for 615 minutes per day.What is the minimum cycle time?


A) 34 minutes
B) 4.7 minutes
C) 92 minutes
D) 130 minutes
E) 615 minutes