Multiple Choice
In theory of constraints scheduling, the __________ refers to the schedule and the __________ refers to inventory used to ensure that the bottleneck is never idle.
A) rope; drum
B) drum; rope
C) drum; buffer
D) buffer; drum
E) buffer; rope
Correct Answer:

Verified
Correct Answer:
Verified