The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received:
The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received:   If he uses the shortest processing time first priority rule to schedule these jobs, what will be the average number of jobs in his shop today? A) 0 B) 1 C) 2 D) 3 E) 4
If he uses the shortest processing time first priority rule to schedule these jobs, what will be the average number of jobs in his shop today?


A) 0
B) 1
C) 2
D) 3
E) 4