Multiple Choice
Job X, which has a duration of four days, is due by the close of business on Friday, December 23. Without looking at the work already scheduled on X's required resource, the scheduler schedules X to be begun on the morning of Tuesday, December 20. This is an example of
A) infinite scheduling.
B) finite scheduling.
C) forward scheduling.
D) backward scheduling.
E) prioritization.
Correct Answer: