In a Master Schedule, the Planning Horizon Is Often Separated

Question 73

Multiple Choice

In a master schedule, the planning horizon is often separated into a series of time periods called


A) pegging.
B) lead times.
C) stacked lead times.
D) time buckets.
E) firm, fixed, and frozen.