Multiple Choice
In MRP, under lot-for-lot ordering, planned-order receipts are
A) identical to scheduled receipts.
B) identical to net requirements.
C) open orders (that is, ordered before the first time bucket, but not delivered yet) .
D) gross requirements.
E) available-to-promise inventory.
Correct Answer:

Verified
Correct Answer:
Verified