Multiple Choice
MRP is used to answer what three questions?
A) What is needed? / Who is needed? / How much is needed?
B) Where it is needed? / When it is needed? / What is needed?
C) When is it needed? / How much is needed? / What is needed?
D) How much is needed? / Why it is needed? / When it is needed?
E) Why it is needed? / What is needed? / Where it is needed?
Correct Answer:

Verified
Correct Answer:
Verified