Multiple Choice
Daily usage is exactly 60 gallons per day. Lead time is normally distributed with a mean of 10 days and a standard deviation of 2 days. What is the standard deviation of demand during lead time?
A) 60 times 2
B) 60 times the square root of 2
C) 60 times the square root of 10
D) 60 times 10
E) 10 times the square root of 2
Correct Answer:

Verified
Correct Answer:
Verified
Q98: The rate of demand is an important
Q99: Which system keeps track of the items
Q100: Profit margins tend to be inversely related
Q101: A nonlinear cost related to order size
Q102: Which of the following is typically the
Q104: In the single-period model, if excess cost
Q105: EOQ inventory models are basically concerned with
Q106: ROP models assume that demand during lead
Q107: In the basic EOQ model, if D
Q108: Weekly demand for a particular item averages