The Materials Manager for a Billiard Ball Maker Must Periodically

Question 6

Multiple Choice

The materials manager for a billiard ball maker must periodically place orders for resin, one of the raw materials used in producing billiard balls. She knows that manufacturing uses resin at a rate of 50 kilograms each day, and that it costs $0.04 per day to carry a kilogram of resin in inventory. She also knows that the order costs for resin are $100 per order, and that the lead time for delivery is four days. At what point should resin be reordered?


A) 0 kilograms remaining
B) 50 kilograms remaining
C) 200 kilograms remaining
D) 400 kilograms remaining
E) 500 kilograms remaining