Multiple Choice
Which of the following would not be a strategy associated with adjusting aggregate capacity to meet expected demand?
A) Subcontract.
B) Vary the size of the workforce.
C) Schedule overtime.
D) Allow inventory levels to vary.
E) Use back orders.
Correct Answer: