    If Forecast Revenue Was $45,000 and Actual Was $39,000 What
Solved

If Forecast Revenue Was $45,000 and Actual Was $39,000 What

Question 7

Question 7

Multiple Choice

If forecast revenue was $45,000 and actual was $39,000 what is the percentage of variance?


A) 13.30%
B) 15.10%
C) No variance
D) 18.00%

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q1: Variance analysis is:<br>A) A means of staying

Q2: If your food and beverage to sales

Q3: In the context of event budgets, allocating

Q4: if you had 300 people attending an

Q5: A budget is a means of:<br>A) Control<br>B)

Q6: Which of the following is the most

Q8: GST reporting for goods and services tax

Q9: A budget is:<br>A) An end-of-year report<br>B) A

Q10: Benchmarks for event management are more difficult

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines