Multiple Choice
On 1 January 2014, Peter Ltd signed a contract worth $64 000 000 to construct the Cycling Stadium. The stadium was to be built over three years, with progress payments as follows:
Estimated costs were $50 000 000. The project was 35 per cent complete at the end of 2014, 75 per cent complete at the end of 2015 and 100 per cent complete at the end of 2016. Revenues and costs were as estimated. How much profit was earned during 2015 if the percentage of completion method was used?
A) $5 600 000
B) $4 375 000
C) $3 500 000
D) $10 500 000
Correct Answer:

Verified
Correct Answer:
Verified
Q3: Highrise Constructions Ltd had a large three-year
Q5: The profit for a particular project of
Q12: With respect to services provided, it is
Q14: Which of the following is NOT necessary
Q16: The profit for a particular project of
Q19: On 1 January 2015, Romulus Ltd signed
Q21: The income statement of Berrima Barbed Wire
Q23: At what point would you expect revenue
Q27: The income statement of Berrima Barbed Wire
Q38: At what point would you expect the