Multiple Choice
On 1 January 2014, Peter Ltd signed a contract worth $64 000 000 to construct the Cycling Stadium. The stadium was to be built over three years, with progress payments as follows:
Estimated costs were $50 000 000. The project was 35 per cent complete at the end of 2014, 75 per cent complete at the end of 2015 and 100 per cent complete at the end of 2016. Revenues and costs were as estimated. How much profit was earned during 2016 if the percentage of completion method was used?
A) $3 500 000
B) $5 600 000
C) $6 343 750
D) $14 000 000
Correct Answer:

Verified
Correct Answer:
Verified
Q4: Revenue from a credit sale should not
Q10: Junction Company had the following transactions,among others,during
Q11: Leslie Ltd has found an error in
Q18: Multi-Storey Builders Ltd had a large three-year
Q19: Revenue recognition means that:<br>A) revenue is not
Q25: The percentage of completion profit for a
Q38: On 1 January 2015, Romulus Ltd signed
Q39: Holidays Ltd manufactures caravans. Transactions for the
Q45: Multi-Storey Builders Ltd had a large three-year
Q46: Highrise Constructions Ltd had a large three-year