Multiple Choice
In order to build spas ready to be installed, there are only about six tasks that have to be completed. An operations manager determines how long it will take to complete each of these tasks. What scheduling device would be most appropriate for this relatively uncomplicated manufacturing process?
A) Gantt chart
B) Enterprise materials planning
C) Critical path assessment
D) Statistical process control
E) Flexible manufacturing diagram
Correct Answer:

Verified
Correct Answer:
Verified
Q137: All the activities managers engage in to
Q138: Product extension and refinement<br>A) shorten the product
Q139: Chevron and other refiners emphasize material resources
Q140: A product layout is often referred to
Q141: ABC Company<br>ABC Company is dedicated to operations
Q143: What is the purpose of quality control?
Q144: To produce a BMW sport-utility vehicle, an
Q145: The choice of a particular location for
Q146: Jennifer is a manager in a circuit
Q147: When Taco Bell determines what different food