Multiple Choice
An example of a project phase in a predictive project is ____.
A) gathering information about the user's needs"
B) performing a project cost/benefit analysis"
C) planning the project"
D) drawing the system interface"
Correct Answer:

Verified
Correct Answer:
Verified