Multiple Choice
Cover measurement commences at the top surface of any direct burial wiring method and ends at the ____ of the finished grade's top surface.
A) closest point
B) midpoint
C) farthest point
D) adjacent corner
Correct Answer:

Verified
Correct Answer:
Verified