Multiple Choice
In , the project manager is responsible for the project results, while the functional managers are responsible for providing the resources needed to achieve the results.
A) an autonomous project organisational structure
B) a functional organisational structure
C) a matrix organisational structure
D) a project management office
Correct Answer:

Verified
Correct Answer: