    In , Project Team Members Can Inform the Project Manager
Solved

In , Project Team Members Can Inform the Project Manager

Question 49

Question 49

Multiple Choice

In , project team members can inform the project manager and the functional manager.


A) an autonomous project organisational structure
B) a functional organisational structure
C) a matrix organisational structure
D) a project management office

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q44: A disadvantage of a functional organisational structure

Q45: A disadvantage of a functional organisational structure

Q46: is found primarily in companies that are

Q47: In , the project organisation is highly

Q48: In , all the resources needed to

Q50: A disadvantage of a matrix organisational structure

Q51: A disadvantage of a functional organisational structure

Q52: can be cost-inefficient both for individual projects

Q53: also facilitates information flow.<br>A)An autonomous project organisational

Q54: A disadvantage of a functional organisational structure

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines