Whenever a Customer Requests Changes, the Project Manager Should

Question 42

Multiple Choice

Whenever a customer requests changes, the project manager should


A) do a quick estimate and say if the change is okay or not.
B) have the appropriate project team members estimate the effects on the project cost and schedule.
C) stop the project's progress.
D) ignore the request and deliver the product promised.